Our grid connection process
How to connect to the grid
Transpower's connection process adapts to fit the needs of your connection. For a small, discrete and simple connection you may be up and running on the National Grid in fewer than 18 months depending on demand and resource availability. Large-scale complex connections may take longer than three years to commission.
Step One: Contact us and discuss your requirements
Step Two: We will send you a Concept Assessment Questionnaire(https://www.transpower.co.nz/concept-assessment-questionnaire) and if applicable a Transpower Services Agreement. One of our subject matter experts will assess your request and requirements. Our standard concept assessment turnaround time is 35-45 working days depending on levels of inquiry and the complexity of each case.
Improving the grid connection process
During 2025 we are reviewing our process for new connections as part of our commitment to continuous improvement. Ultimately, this will get customers connected sooner. We plan to make impactful changes giving customers and Transpower more certainty earlier on.
When we start the first stage of investigation we will be in touch to talk through the journey, work through connection options and set the direction for our work together.
Process improvements will be identified over the next few months, ensuring we arrive at an agreed single connection solution as early as possible, with clearer pathways, cost estimates and a timeline for the next stage.
We’ll keep you updated as we identify and work through refinements to the process.
Your Customer Journey
The image below shows a typical customer journey with Transpower from initial contact through to ongoing operations, lifecycle replacement and connection enhancements. We can be flexible to meet your needs, so your journey may take a different path.
Image
More information on customer journey contracts(https://www.transpower.co.nz/our-work/industry/customer-contract-information).
Our tailored approach
We want to work with you to ensure your new generation project is a success. Connecting new generation to the power system takes careful and coordinated planning.
The New Zealand power system is run on open access principles. You can request to build and connect anywhere you want but Transpower will always need to manage the integrity and security of the transmission system. You cannot buy or reserve transmission capacity on the transmission system.
Please engage with us early so that Transpower (as Grid Owner and System Operator), our service provider network and your own teams and service providers can meet your expectations in delivering on an expanding programme of work.
If you are building new generation greater than 1 MW you will need to comply with the Electricity Authority’s Code and Compliance(https://www.ea.govt.nz/code-and-compliance/) and engage with Transpower in our role as System Operator. Read GL-EA-404 Generation Commissioning Process(https://static.transpower.co.nz/public/bulk-upload/documents/GL-EA-404 Generation Commissioning Process.pdf?VersionId=QyOhYITWvTOTbF8TNK8CMxxa_JwojsLE), or refer to the System Operator's Commissioning Generation(https://www.transpower.co.nz/system-operator/information-industry/asset-owner-requirements/commissioning-generation) page.
Most small assets (<40 MW) choose to connect via the local distributor's network as transmission level connections tend to be more expensive. At some sites a transmission level connection can still be a cost effective option.
Medium-sized assets need to consider the costs and capacity of both options. This should include an assessment on the impact on transmission pricing for you and the distribution company. You can talk to Transpower and the local distribution company about potential implications including connection charges.